Detailed estimate: Project-specific

A project-specific contract requires a highly detailed estimate of the cost of the work. The CM, with the assistance of the functional manager and/or project manager, bases this estimate primarily on the hours necessary to complete every identified task for a project.

 

 

Projects

Tasks

Project/task-order based

Scope of Work

x

 

 

State’s Estimate

x

 

 

 

 

 

Project-specific

Scope of Work

 

x

 

State’s Estimate

 

x

The CM works with the functional units to develop the estimate for the whole project by:

  • breaking the scope of work into its component tasks or milestones (WBS level 7 or lower)
  • estimating the hours of each task/milestone
  • applying the hourly rates plus other direct costs and fee (profit)
  • creating a summary sheet with a total estimated cost

Sample on-call Director's Estimate