header
Contract Procurement : Knowledge Check

Module 3 Knowledge Check

  1. The procurement phase of A&E contracting begins with a formal request to enlist a consultant. What form and package is completed by the Contract Manager and submitted electronically to the DPAC Coordinator?

    ADM 360

    Std. 215

    ADM 2031

    ADM 0248


  2. The Request for Qualification (RFQ) is a solicitation document that is advertised and reviewed by consultants. What document do consultants submit in response to a RFQ?

    Proposal

    Quote

    Bid

    Statement of Qualifications (SOQ)


  3. DPAC determines if the submittal is responsive. DPAC rejects non-responsive SOQs. Which one of the answers below is non-responsive to the solicitation requirements?

    Submittal sent on time (date and time)

    Submittal sent to proper location

    Submittal did not include all the attachments

    Submittal included all the copies required


  4. To develop a Short List of responsive SOQs, each member of the consultant selection committee independently evaluates each proposal in terms of the technical criteria listed in the RFQ. What is the form number that is used to rate the SOQs?

    ADM 2028

    ADM 2027

    ADM 360

    ADM 2031


  5. After the short list is completed for HQ Division contracts, who is responsible for scheduling consultant interviews, securing interview rooms for needed dates and times, and inviting Department interview panel members for the final interview to select the top ranked consultant?

    Contract Manager

    DPAC coordinator

    DPAC contract analyst

    DPAC Scheduler


  6. For A&E contracts, when do the consultants provide their sealed cost proposals to the Department?

    With the SOQ

    At the interview of the Short Listed consultants

    When the final top ranked consultant is selected

    Within 5 working days after final top ranked consultant is selected


  7. What form number is used by each member of the consultant selection committee to independently score each shortlisted firm to develop the final ranking of the most qualified consultants? The scores from each panel member are combined to come up with the final ranking of the consultant.

    ADM 2028

    ADM 2027

    ADM 360

    ADM 2031


  8. Once the contract has been executed, who provides, upon request, a debriefing for any non-selected firms?

    Task Order Manager

    Contract Manager or designated member of the consultant selection committee

    DPAC contract analyst

    DPAC Scheduler


  9. If fewer than 3 responsive SOQs are received, it may be necessary to re-advertise the RFQ. (True or False).

    True

    False


  10. Who is responsible to prepare the interview questions with assistance from members of the consultant selection committee, and forwards the questions to the DPAC?

    DPAC Coordinator

    DPAC Contract Analyst

    DPAC Scheduler

    Contract Manager